Transformer Assembly Line · Station Cycle Time & Scheduler Dashboard
| Station | Record | Avg Actual | Deviation |
|---|---|---|---|
| Station 1 | 1h 00m | 0h 48m | −20% |
| Station 2 | 0h 48m | 1h 18m | +63% |
| Station 3 | 1h 30m | 0h 54m | −40% |
| Station 4 | 1h 06m | 0h 43m | −35% |
Hours:minutes per unit, by station
The line scheduler paces new jobs off each station's trailing 3-month average actual cycle time — not the original cycle-time-of-record — so the schedule reflects how the line really runs, including Station 2 running well over its cycle time of record.
| Station | Avg Actual | Deviation | Scheduled Takt |
|---|---|---|---|
| Station 1 | 0h 48m | −20% | 1h 00m |
| Station 2 | 1h 18m | +30% | 1h 00m |
| Station 3 | 0h 54m | −10% | 1h 00m |
| Station 4 | 0h 43m | −35% | 0h 45m |
Deliver to schedules based on actual cycle times and measure labor input to optimize scheduling.